Question: Suppose that a task in a project has the following time estimates: to = optimistic completion time = 8 weeks tm = most likely completion

Suppose that a task in a project has the

Suppose that a task in a project has the following time estimates: to = optimistic completion time = 8 weeks tm = most likely completion time = 11 weeks to = pessimistic completion time = 14 weeks Compute the expected task completion time. The expected task completion time is weeks. (Enter your response rounded to one decimal place.)