Question: Suppose that the normal time for activity C is 1 0 weeks with a normal cost of $ 6 , 0 0 0 . We

Suppose that the normal time for activity C is 10 weeks with a normal cost of $6,000. We can crash it to only 4 weeks at a total cost of $12,000.The total activity cost if we crash it to 7 weeks will beA.$9,000.B.$11,000.C.$8,000.D.$6,000.