Question: Suppose that the normal time for activity G is 8 weeks with a normal cost of $5,000. We can crash it to only 5 weeks

Suppose that the normal time for activity G is 8 weeks with a normal cost of $5,000. We can crash it to only 5 weeks with the crash cost of $8,000.

What will be the total activity cost if we crash it to 6 weeks ?

SIDE NOTE*** THE ANSWER TO THIS IS 7,000 I NEED HELP SOLVING