Question: Suppose we have a school building project. The expected project duration and its variance are 35 weeks and 9 respectively. Those project parameters are determined

Suppose we have a school building project. The
Suppose we have a school building project. The expected project duration and its variance are 35 weeks and 9 respectively. Those project parameters are determined by using PERT Technique. If we want a 90% level of confidence, what should the project duration be? (2 points) 39.8 weeks 35 weeks O 38.9 weeks 044 weeks