Question: Suppose we have a school building project. The expected project duration and its variance are 35 weeks and 9 respectively. Those project parameters are determined

Suppose we have a school building project. The

Suppose we have a school building project. The expected project duration and its variance are 35 weeks and 9 respectively. Those project parameters are determined by using PERT Technique. If we want a 90% level of confidence, what should the project duration * be? (2 points) 38.9 weeks o 39.8 weeks o 44 weeks o 35 weeks