Question: Suppose we have a school building project. The expected project duration and its variance are 35 weeks and 9 respectively. Those project parameters are determined

Suppose we have a school building project. The
Suppose we have a school building project. The expected project duration and its variance are 35 weeks and 9 respectively. Those project parameters are determined by using PERT Technique. Determine the probability of finishing the project within 38 days. (2 points) O 16% O 84% O 63% O 37%