Question: Suppose we have a school building project. The expected project duration and its variance are 35 weeks and 9 respectively. Those project parameters are determined

Suppose we have a school building project. The expected project duration and its variance are 35 weeks and 9 respectively. Those project parameters are determined by using PERT Technique. If we want a 95% level of confidence, what should the project duration be? (2 points) O 39.8 weeks 38.9 weeks O 35 weeks O 44 weeks
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
