Question: Tabke 1 - 1 : table [ [ , , Most,, ] , [ , Immediate,Optimistic,Likely,Pessimistic ] , [ Activity , Predecessor,Time,Time,Time ] ,

Tabke 1-1:
\table[[,,Most,,],[,Immediate,Optimistic,Likely,Pessimistic],[Activity,Predecessor,Time,Time,Time],[A,-,2,8,14],[B,-,8,8,8],[C,A,6,9,18],[D,B,5,11,17]]
According to the Table 1-1, what is the critical path?
 Tabke 1-1: \table[[,,Most,,],[,Immediate,Optimistic,Likely,Pessimistic],[Activity,Predecessor,Time,Time,Time],[A,-,2,8,14],[B,-,8,8,8],[C,A,6,9,18],[D,B,5,11,17]] According to the Table 1-1, what is the