Question: Table 1 - The Krugersdorp Examination Block Construction Project table [ [ table [ [ Activity ] , [ No . ] ]

Table 1- The Krugersdorp Examination Block Construction Project
\table[[\table[[Activity],[No.]],\table[[Activity],[Description]],\table[[Duration],[(Weeks)]],\table[[Predecessor],[Activity]]],[A,\table[[Clear],[ground]],3,--],[B,\table[[Dig],[foundation]],4,A],[C,\table[[Procure],[cement]],2,A],[D,\table[[Sink],[columns]],5,B],[E,\table[[Procure],[floor mash]],1,C],[F,\table[[Pour],[concrete]],2,C],[G,\table[[Leave],[concrete to],[dry]],4,D;E],[H,\table[[Inspect],[foundation]],1,F;G]]
2.1 Use the activities in Table 1 to draw the network diagram.
(8)
2.2 Calculate the critical path (CP) for this project.
(4)
2.3 Calculate the earliest start (ES) and the earliest finish (EF) for all the activities in this project and complete the table below.
(8)
\table[[Activity No.,ES,EF],[A,,],[B,,],[C,,],[D,,],[E,,],[F,,],[G,,],[H,,]]
2.4 What is the late start (LS) for Activity F?
(1)
2.5 Project milestones are used to measure the progress of a project. When a project reaches a particular milestone, you need to answer a few questions. Please list those questions.
(4)
 Table 1- The Krugersdorp Examination Block Construction Project \table[[\table[[Activity],[No.]],\table[[Activity],[Description]],\table[[Duration],[(Weeks)]],\table[[Predecessor],[Activity]]],[A,\table[[Clear],[ground]],3,--],[B,\table[[Dig],[foundation]],4,A],[C,\table[[Procure],[cement]],2,A],[D,\table[[Sink],[columns]],5,B],[E,\table[[Procure],[floor mash]],1,C],[F,\table[[Pour],[concrete]],2,C],[G,\table[[Leave],[concrete to],[dry]],4,D;E],[H,\table[[Inspect],[foundation]],1,F;G]]

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!