Question: Table 1 - The Krugersdorp Examination Block Construction Project table [ [ table [ [ Activity ] , [ No . ] ]
Table The Krugersdorp Examination Block Construction Project
tabletableActivityNotableActivityDescriptiontableDurationWeekstablePredecessorActivityAtableCleargroundBtableDigfoundationACtableProcurecementADtableSinkcolumnsBEtableProcurefloor mashCFtablePourconcreteCGtableLeaveconcrete todryD;EHtableInspectfoundationF;G
Use the activities in Table to draw the network diagram.
Calculate the critical path CP for this project.
Calculate the earliest start ES and the earliest finish EF for all the activities in this project and complete the table below.
tableActivity NoESEFABCDEFGH