Question: Table 7.2 Using Table 7.2, what is the earliest expected time of completion of the whole project? greater than 24 weeks fewer than or equal
Table 7.2 Using Table 7.2, what is the earliest expected time of completion of the whole project?
greater than 24 weeks
fewer than or equal to 19 weeks
greater than 19 but fewer than or equal to 21 weeks
greater than 21 but fewer than or equal to 24 weeks