Question: Table 7.5 Activity Predecessor Time (days) A -- 8 B -- 6 C -- 3 D A,B 10 E C 8 F A 5 G

Table 7.5

Activity

Predecessor

Time (days)

A

--

8

B

--

6

C

--

3

D

A,B

10

E

C

8

F

A

5

G

D,E

3

H

G

4

Using Table 7.5, how many days can activity C be delayed without changing the whole project's earliest completion time?