Question: Table 7.5 Activity Predecessor Time (days) A -- 8 B -- 6 C -- 3 D A,B 10 E C 8 F A 5 G
Table 7.5
| Activity | Predecessor | Time (days) |
| A | -- | 8 |
| B | -- | 6 |
| C | -- | 3 |
| D | A,B | 10 |
| E | C | 8 |
| F | A | 5 |
| G | D,E | 3 |
| H | G | 4 |
Using Table 7.5, how many days can activity C be delayed without changing the whole project's earliest completion time?