Question: table [ [ A , None, 3 ] , [ B , None, 5 ] , [ C , None, 4 ] , [

\table[[A,None,3],[B,None,5],[C,None,4],[D,A, B,3],[E,B, C,9],[F,E,4],[G,E,4],[H,F, G,6]]
A - Draw the network diagram with early and late start time and early and late finish time of each task, and identify the critical path? (8)
 \table[[A,None,3],[B,None,5],[C,None,4],[D,A, B,3],[E,B, C,9],[F,E,4],[G,E,4],[H,F, G,6]] A - Draw the network diagram with