Question: table [ [ Activity , Activity Description,Duration,Predecessors ] , [ A , Conduct competitive analysis, 3 , - ] , [ B , Review

\table[[Activity,Activity Description,Duration,Predecessors],[A,Conduct competitive analysis,3,-],[B,Review field sales reports,2,A],[C,Conduct tech capabilities assessment,5,A],[D,Develop focus group data,2,A, B, C],[E,Conduct telephone surveys,3,D],[F,Identify relevant specification improvements,3,E],[G,Interface with marketing staff,1,F],[H,Develop engineering specifications,5,G],[I,Check and debug designs,4,H],[J,Develop testing protocol,3,G],[K,Identify critical performance levels,2,J],[L,Assess and modify product components,6,I, K],[M,Conduct capabilities assessment,12,L],[N,Identify selection criteria,3,M],[O,Develop RFQ (Request for Quote),4,M],[P,Develop production master schedule,5,N, O],[Q,Collaborate with sales staff,1,P],[R,Prepare product launch,3,Q]]
Identify the total Duration:
A)34 days
B)55 days
C)57 days
D)62 days
 \table[[Activity,Activity Description,Duration,Predecessors],[A,Conduct competitive analysis,3,-],[B,Review field sales reports,2,A],[C,Conduct tech capabilities assessment,5,A],[D,Develop focus

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!