Question: table [ [ Activity , Predecessor,Duratio ] , [ A , NONE, 2 ] , [ B , A , 4 ] , [

\table[[Activity,Predecessor,Duratio],[A,NONE,2],[B,A,4],[C,A,3],[D,A,2],[E,B,3],[F,C,6],[G,C,D,5],[H,E,F,6],[I,G,5],[J,H,I,5]]
Part A
Draw a project network diagram from the above information.
Activities B and H can be shortened to a minimum of 2 weeks; which activity would you shorten to reduce the project duration by 2 weeks?
Why?
Explain the risk associated with leveling resources, compressing or crashing projects, and imposed duration(s) or "catch-up" as the project is being implemented.
 \table[[Activity,Predecessor,Duratio],[A,NONE,2],[B,A,4],[C,A,3],[D,A,2],[E,B,3],[F,C,6],[G,C,D,5],[H,E,F,6],[I,G,5],[J,H,I,5]] Part A Draw a project network diagram from the above

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!