Question: table [ [ Activity , Time ( weeks ) , Immediate Predecessor ( s ) , Activity,Time ( we ] , [ A ,

\table[[Activity,Time (weeks),Immediate Predecessor(s),Activity,Time (we],[A,6,-,E,4],[B,6,-,F,7],[C,2,A,G,10],[D,1,A,H,8],[,,,,],[,,Activity,ES,EF],[,A,0,6,],[,B,0,6,],[,C,6,8,],[,D,6,7,],[,E,6,10,],[,F,6,13,],[,G,10,20,],[,H,13,21,],[,,,,]]
Dave's latest start (LS) and latest finish (LF) are:
\table[[Activity,LS,LF],[H,13,],[G,11,],[F,6,],[E,7,],[D,12,],[C,9,],[B,0,],[A,3,]]
The slack times are:
ActivitySlackABCDEFGH
The activities on the critical path are
The total project completion time for Dave = weeks .
 \table[[Activity,Time (weeks),Immediate Predecessor(s),Activity,Time (we],[A,6,-,E,4],[B,6,-,F,7],[C,2,A,G,10],[D,1,A,H,8],[,,,,],[,,Activity,ES,EF],[,A,0,6,],[,B,0,6,],[,C,6,8,],[,D,6,7,],[,E,6,10,],[,F,6,13,],[,G,10,20,],[,H,13,21,],[,,,,]] Dave's latest start (LS) and latest finish

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!