Question: table [ [ Activity , Time ( weeks ) , Immediate Predecessor ( s ) , Activity,Time ( we ] , [ A ,
tableActivityTime weeksImmediate PredecessorsActivity,Time weAEBFCAGDAHActivity,ESEFABCDEFGH
Dave's latest start LS and latest finish LF are:
tableActivityLSLFHGFEDCBA
The slack times are:
The activities on the critical path are
The total project completion time for Dave weeks