Question: The Table below shows the activities, immediate predecessors and activity durations of a project. Draw the AON project network. How long would it take to

The Table below shows the activities, immediate predecessors and activity durations of a project.

  1. Draw the AON project network.
  2. How long would it take to complete this project?
  3. What is the length of the critical path?

ACTIVITY

IMMEDIATE PREDECESSOR(S)

TIME (DAYS)

A

2

B

A

4

C

A

4

D

B

6

E

D

9

F

C

8

G

E, F

2

H

G

2

I

G

3

J

H, I

4

K

J

4