Question: The Table below shows the activities, immediate predecessors and activity durations of a project. Draw the AON project network. How long would it take to
The Table below shows the activities, immediate predecessors and activity durations of a project.
- Draw the AON project network.
- How long would it take to complete this project?
- What is the length of the critical path?
| ACTIVITY | IMMEDIATE PREDECESSOR(S) | TIME (DAYS) |
| A | 2 | |
| B | A | 4 |
| C | A | 4 |
| D | B | 6 |
| E | D | 9 |
| F | C | 8 |
| G | E, F | 2 |
| H | G | 2 |
| I | G | 3 |
| J | H, I | 4 |
| K | J | 4 |