Question: table [ [ WBS Element, table [ [ Planned Value ] , [ PV ) ] ] , table [ [ Earned

\table[[WBS Element,\table[[Planned Value],[ PV)]],\table[[Earned Value],[(EV)]],\table[[Actual Cost],[(AC)]]],[2.01 Airframe,48000,48000,50000],[2.02 Engines,22000,21000,23000],[2.03 Avionics,80000,60000,45000],[2.04 Communications,30000,30000,30000],[2.05 Tech. Manuals,42000,40000,48000],[2.06 Spares,40000,35000,42000],[2.07 Training,80000,80000,86000],[Project Total,342000,314000,324000]]
Figure 14.1 Drug Surveillance Aircraft Project - Monthly Performance Report (October 31,20XX)
Consider the project performance report presented in figure 14.1. As a project manager, these results should lead you to...
Select one:
a. take actions to understand and remedy the schedule performance on the active avionics work packages.
b. take actions to understand and resolve budgetary overruns on the active communications work packages.
 \table[[WBS Element,\table[[Planned Value],[ PV)]],\table[[Earned Value],[(EV)]],\table[[Actual Cost],[(AC)]]],[2.01 Airframe,48000,48000,50000],[2.02 Engines,22000,21000,23000],[2.03 Avionics,80000,60000,45000],[2.04 Communications,30000,30000,30000],[2.05 Tech.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!