Question: Task 16Question 16 The last workstation in a production process performs final assembly of a product that is needed daily on 960 units. The workstation
Task 16Question 16
The last workstation in a production process performs final assembly of a product that is needed daily on 960 units. The workstation receives semi-finished products from the previous workstation in containers containing 20 units. It takes 40 minutes from the time semi-finished products are ordered until they are available in the terminal's input buffer. The uncertainty in lead time means that you need a safety stock that corresponds to 25% of demand during lead time. You work 8 hours a day in the production flow.
How many kanban are needed in the above situation?