Question: Task Budget Duration ( days ) Immediate Predecessors Shortest Time Possible Acceleration Cost per day A $ 2 0 0 2 None 2 B $

Task Budget Duration (days)
Immediate Predecessors Shortest Time Possible Acceleration Cost per day
A $2002 None 2
B $5005 A 3 $30
C $2002 B 1 $15
D $4004 A 4
E $3003 B&D 1 $20
F $4004 E&C 2 $40
a.(4 Points) Identify the critical path by forward and backward paths. For the tasks
that are not on the critical path, identify their slacks.