Question: Consider the following information about a small project: Task Budget Duration (days) Immediate Predecessors Shortest Time Possible Acceleration Cost per day A $200 2 None
Consider the following information about a small project: Task Budget Duration (days) Immediate Predecessors Shortest Time Possible Acceleration Cost per day A $200 2 None 2 B $500 5 A 3 $30 C $200 2 B 1 $15 D $400 4 A 4 E $300 3 B&D 1 $20 F $400 4 E&C 2 $40 a. (4 Points) Identify the critical path by forward and backward paths. For the tasks that are not on the critical path, identify their slacks.