Question: QUESTION 1 Task C has two immediate predecessors, Tasks A and B. Task A has an early finish time of 4 days, and Task Bhas

QUESTION 1 Task C has two immediate predecessors,
QUESTION 1 Task C has two immediate predecessors, Tasks A and B. Task A has an early finish time of 4 days, and Task Bhas an early finish time of 6 days What is the early start time of Task