Question: Task E has two immediate predecessors, B and C . Task B is planned to take 7 days to complete; task C is planned to

Task E has two immediate predecessors, B and C. Task B is planned to take 7 days to complete; task
C is planned to take 11 days. The early start time for both tasks is October 15. The actual start dates
for tasks B and C are October 16 and October 15, respectively. At the end of October 19, task B is
assessed to be 40 percent completed and task C,75 percent completed. What is the expected early
start time for task E?