Question: Task E has two immediate predecessors, B and C . Task B is planned to take 7 days to complete; task C is planned to
Task E has two immediate predecessors, B and C Task B is planned to take days to complete; task
C is planned to take days. The early start time for both tasks is October The actual start dates
for tasks B and C are October and October respectively. At the end of October task B is
assessed to be percent completed and task C percent completed. What is the expected early
start time for task E