Question: Task Immediate Predecessor ( s ) Duration ( days ) A - - - - - 2 B - - - - - 4 C

Task Immediate Predecessor(s) Duration (days)
A -----2
B -----4
C -----8
D A, B 1
E B, C, D 6
F E 3
a. How many paths are there in this project network?