Question: Task Immediate predecessors ESTIMATED TIME VARIANCE A - 8.83 1.36 B - 9 1 C B 7 0.11 D A 4 0.44 E A,D 8
| Task | Immediate predecessors | ESTIMATED TIME | VARIANCE |
| A | - | 8.83 | 1.36 |
| B | - | 9 | 1 |
| C | B | 7 | 0.11 |
| D | A | 4 | 0.44 |
| E | A,D | 8 | 1 |
Expected completion time of the project?
Draw the network diagram ?
Probability of completing in 15 days or less ?
Probability of completing the project in 24 days or less?
Probability of completing the project in 120 days or less?