Question: Task Predecessors Duration (days) A - 3 B - 5 C A,B 6 D C 1 E C,F 6 F - 1 G - 6
| Task | Predecessors | Duration (days) |
| A | - | 3 |
| B | - | 5 |
| C | A,B | 6 |
| D | C | 1 |
| E | C,F | 6 |
| F | - | 1 |
| G | - | 6 |
What is the project duration in days?
What is the critical path?