Question: Task Predecessors Duration (days) A - 3 B - 5 C A,B 6 D C 1 E C,F 6 F - 1 G - 6

Task Predecessors Duration (days)
A - 3
B - 5
C A,B 6
D C 1
E C,F 6
F - 1
G - 6

What is the project duration in days?

What is the critical path?