Question: Task Status Planning Section 1 Build Section 2 Build 150/150 320/500 150/600 0/100 Completion Using the project information above, and calculate the Current Earned Value?

Task Status Planning Section 1 Build Section 2 Build 150/150 320/500 150/600 0/100 Completion Using the project information above, and calculate the Current Earned Value? d. 31% b. 45.9% C. 31.7% d. 62%