Question: Using the project information below, what is the current earned value? Task Status Planning 150/150 Section 1 Build 320/500 Section 2 Build 150/600 Completion 0/100
Using the project information below, what is the current earned value?
Task Status Planning 150/150 Section 1 Build 320/500 Section 2 Build 150/600 Completion 0/100