Question: Task time estimates for a production line setup project at Kitimat LPG factory beginning during the fourth ( 4 ) week are as follows: Activity

Task time estimates for a production line setup project at Kitimat LPG factory beginning during the fourth (4) week are as follows:
Activity Time (in hours) Immediate Predecessors
A 16.0-
B 17.2-
C 15.0 A
D 16.0 B, C
E 14.5 B, C
F 17.7 D
G 14.0 E, F
a) Draw the project network using Activity on the Node (AON).
b) Determine the ES, EF, LS, LF and the slack for each activity.
c) What is the expected project length?
d) Identify the critical path.
e) Using the information draw a Gantt chart for the project.