Question: Task time estimates for a production line setup project at Kitimat LPG factory beginning during the fourth ( 4 ) week are as follows: Activity
Task time estimates for a production line setup project at Kitimat LPG factory beginning during the fourth week are as follows:
Activity Time in hours Immediate Predecessors
A
B
C A
D B C
E B C
F D
G E F
a Draw the project network using Activity on the Node AON
b Determine the ES EF LS LF and the slack for each activity.
c What is the expected project length?
d Identify the critical path.
e Using the information draw a Gantt chart for the project.