Question: Task time estimates for a production line setup project at Robert Klassens Ontario factory are as follows: Activity Immediate Predecessor(S) Activity Time (days) A ---
- Task time estimates for a production line setup project at Robert Klassens Ontario factory are as follows:
| Activity | Immediate Predecessor(S) | Activity Time (days) |
| A | --- | 6.0 |
| B | --- | 7.2 |
| C | A | 5.0 |
| D | B, C | 6.0 |
| E | B, C | 4.5 |
| F | D | 7.7 |
| G | E,F | 4.0 |
Draw the project using AON. Identify the critical path What is the expected project length