Question: Task time estimates for a production line setup project at Robert Klassens Ontario factory are as follows: Activity Immediate Predecessor(S) Activity Time (days) A ---

  1. Task time estimates for a production line setup project at Robert Klassens Ontario factory are as follows:

Activity

Immediate Predecessor(S)

Activity Time (days)

A

---

6.0

B

---

7.2

C

A

5.0

D

B, C

6.0

E

B, C

4.5

F

D

7.7

G

E,F

4.0

Draw the project using AON. Identify the critical path What is the expected project length