Question: Task time estimates for the modification of an assembly line atJim Goodale's Carbondale, Illinois, factory are as follows:stion 1 Activitystion 2 Gstion 3 Time (
Task time estimates for the modification of an assembly line atJim Goodale's Carbondale, Illinois, factory are as follows:stion Activitystion Gstion Timein hours Immediate PredecessorsB CB CDE. FThis exercise contains only parts d b and cstion d Using the line drawing tool five times, draw a Gantt chart for activities C through G of the project based on the early times.Carefully follow the instructions above, and only draw the required objectsstion stion stion le solve thisClear allCheck answerEtext pagesGet more help a