Question: Task time estimates for the modification of an assembly line at Jim Goodale's Carbondale, Illinois, factory are as follows. Figure 1 Activity . Immediate Predecessor(s)

Task time estimates for the modification of an

Task time estimates for the modification of an assembly line at Jim Goodale's Carbondale, Illinois, factory are as follows. Figure 1 Activity . Immediate Predecessor(s) B D E F G Time (in hours) 5.0 6.7 4.0 8.0 4.5 8.1 4.0 B, C B, C D E, F This exercise contains only part a. a) The correct activity-on-node (AON) diagram for the project is shown in Figure 2 Figure 2 Figure 3. Figure 1. Figure 3

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!