The activities required to service a car at a dealer can be viewed as a mini-project...
Fantastic news! We've Found the answer you've been seeking!
Question:
Transcribed Image Text:
The activities required to service a car at a dealer can be viewed as a mini-project summarised in the following table: Activity Description Drain Oil Replace Filter Refill Oil Check Tyres Wash Windows Fill Fluids Final Test A. B. C. D. E. F. ABCDBD G. А с E Table 1: Activity Times and Predecessors Predecessor Activity F G A B, E MON D E C, F Minutes Required Optimistic Most Likely Pessimistic b The variability in times required to perform each activity is due to the different types, sizes and conditions of the cars to be serviced. Round off times to two decimal places where fractional. Draw the activity network for this problem (either AON or AOA) Determine the Expected Time and Variance for each activity. a 2 1 2 2 2 2 0.5 m 3.5 2 2.5 3 3 5 3 4 Show the activity schedule (ES, EF, LS, and LF). Based on your workings in (C.) above, determine the critical path for this project. 4 5 4 1.5 What are the expected time and the variance of the project? Calculate the probability that the project will be finished within 10 minutes. A project manager will use the "Work-Break-Down Structure" to identify the activities needed to complete the project. Explain what is meant by the "Work Break-Down Structure". The activities required to service a car at a dealer can be viewed as a mini-project summarised in the following table: Activity Description Drain Oil Replace Filter Refill Oil Check Tyres Wash Windows Fill Fluids Final Test A. B. C. D. E. F. ABCDBD G. А с E Table 1: Activity Times and Predecessors Predecessor Activity F G A B, E MON D E C, F Minutes Required Optimistic Most Likely Pessimistic b The variability in times required to perform each activity is due to the different types, sizes and conditions of the cars to be serviced. Round off times to two decimal places where fractional. Draw the activity network for this problem (either AON or AOA) Determine the Expected Time and Variance for each activity. a 2 1 2 2 2 2 0.5 m 3.5 2 2.5 3 3 5 3 4 Show the activity schedule (ES, EF, LS, and LF). Based on your workings in (C.) above, determine the critical path for this project. 4 5 4 1.5 What are the expected time and the variance of the project? Calculate the probability that the project will be finished within 10 minutes. A project manager will use the "Work-Break-Down Structure" to identify the activities needed to complete the project. Explain what is meant by the "Work Break-Down Structure".
Expert Answer:
Answer rating: 100% (QA)
A AON Diagram Activity on Node Diagram is a tool that displays the task and the manner in which it is needed to be executed for optimal performance of the project In such a diagram every task is repre... View the full answer
Related Book For
Spreadsheet Modeling & Decision Analysis A Practical Introduction to Management Science
ISBN: 978-0324656633
5th edition
Authors: Cliff T. Ragsdale
Posted Date:
Students also viewed these general management questions
-
The activities required to service a car at Zippy-Lube can be viewed as a mini-project as summarized in the following table. The variability in the time required to perform each activity is due to...
-
A project network is shown below. Use a forward and a backward pass to determine the critical path, and then fill out the table below. Activity times are in weeks. Activity Precedence Activities...
-
On January 1, 2012, Albert invested $1,000 at 6 percent interest per year for three years. The CPI (times 100) on January 1, 2012, stood at 100. On January 1, 2013, the CPI was 105; on January 1,...
-
On November 11, 2011, Wadsworth Company purchased twenty shares of ZZZ for $8 per share. Wadsworth held the investment for the remainder of 2011, and as of December 31, the per-share market value of...
-
Use the superposition principle to find \(v_{\mathrm{O}}\) in Figure P \(_{3}=\) 32 . 15 V | 200 VO | 200 200 +1) 5V
-
Dr. Walter Sullivan was one of several plastic surgeons in Las Vegas visited by Julie Jones. Jones, an exotic dancer, sought plastic surgery to improve her ability to make money in her profession....
-
Zebra Imaginarium, a retail business, had the following cash receipts during December 20--. The sales tax is 6%. Dec. 1 Received payment on account from Michael Anderson, $1,360. 2 Received payment...
-
The figure depicts Jack - in - the - box: "Jack" is attached inside a box by a spring, as shown. You estimate Jack's mass to be 0 . 4 k g . As so often happens, a sign tells you the spring constant:...
-
OTE operates in a stable industry and the results for the company were relatively consistent over the past five years. The December 31 year-end statements are provided in Appendix I. There are a few...
-
Verify if the following function is a wave function or not? h(x,t) = a(x + vt )
-
Which accounts in the general ledger are affected when the monthly posting is mTo be useful, the information outputs of a system should be Pregunta 4Seleccione una: a. distributed only to management...
-
Heedy Sparacia Winery accumulates the costs incurred in the labeling process in an activity cost pool. Costs for the labeling process are estimated to be $340,000, and the winery expects to generate...
-
Jimmy invests $16,000 in an account that pays 5.90% compounded quarterly. How long (in years and months) will it take for his investment to reach $21,000? ___years and ___months
-
CFO Mr. Cruz embezzled P10million from XYZ Corporation. Mr. Cruz has the obligation to: (1) Return the P10million to XYZ Corporation; (2) Pay the salaries of XYZ Corporation employees for one fiscal...
-
Which is an example of a debt danger sign? a. I list down all debts that I have on a notebook. b. I regularly check my credit report and report errors in it. c. I always max out my credit cards when...
-
(4.1) Prove that if a process X, is both a supermartingale and submartingale with respect to {Y} then it is a martingale with respect to {Y}. (4.2) Consider a Markov chain S, which at each transition...
-
The time to assemble the first unit on a production line is 10 hours. The learning rate is 0.94. Approximately how long will it take for the seventh unit to be assembled? The number of hours needed...
-
Bull Dog Express runs a small airline that offers commuter flights between several cities in Georgia. The airline flies into and out of small airports only. These airports have limits on the number...
-
Barbara Roberts recently received $30,000 as a small inheritance from a distant relative. She wants to invest the money so as to earn $900 to buy a notebook computer next year when she enters...
-
Water is delivered throughout New York City using eight main water lines that are connected at six pumping stations as shown in Figure. The numbers on each of the arcs indicates the maximum allowable...
-
Reconsider the data of Problem 31. Data from Problem 31 The following three investment opportunities are available. The returns for each investment for each year vary, but the first cost of each is...
-
The following three investment opportunities are available. The returns for each investment for each year vary, but the first cost of each is $20,000. Based on a future worth analysis, which...
-
Explain the relationship between the finite sample \(F\)-test and the large sample \(\chi^{2}\)-test, and the assumptions under which each is suitable.
Study smarter with the SolutionInn App