Question: The activity times, in three different estimates (optimistic, most likely, and pessimistic), are as follows. Activity Optimistic (a) Most Likely (m) Pessimistic (b) A 2

The activity times, in three different estimates (optimistic, most likely, and pessimistic), are as follows.

Activity Optimistic (a) Most Likely (m) Pessimistic (b)
A 2 6 8
B 6 8 12
C 4 9 15
D 4 5 8
E 2 5 11
F 6 7 9
G 2 4 7
H 3 7 7
What is the
expected time (te) for each activity? Round your calculations to the nearest second decimal point. Show all your work.
What is the critical path, and how long is this project expected to last? Show all your work.