Question: The activity times, in three different estimates (optimistic, most likely, and pessimistic), are as follows. Activity Optimistic (a) Most Likely (m) Pessimistic (b) A 2
The activity times, in three different estimates (optimistic, most likely, and pessimistic), are as follows.
| Activity | Optimistic (a) | Most Likely (m) | Pessimistic (b) |
|---|---|---|---|
| A | 2 | 6 | 8 |
| B | 6 | 8 | 12 |
| C | 4 | 9 | 15 |
| D | 4 | 5 | 8 |
| E | 2 | 5 | 11 |
| F | 6 | 7 | 9 |
| G | 2 | 4 | 7 |
| H | 3 | 7 | 7 |
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
