Question: The answer should be in CPM method A company have to develop a product has following times schedule Activity Times in weeks Activity Times in

The answer should be in CPM method

The answer should be in CPM method A company have

A company have to develop a product has following times schedule Activity Times in weeks Activity Times in weeks 4 8 1 1 1 (1 2) (1 - 3) (2-4) (3 4) (3-5) (4-9) (5-6) (5 7) (6-8) (7-8) (8-9) 2. 1 1 6 8 5 (8 10) (9 10) 7 4 Construct the network and compute 1. TE and TL for each event 2. Float for each activity 3. Critical path and its duration

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!