Question: The AOA network for a certain project is given in the graph below with the task durations ( in days ) in the table beneath

The AOA network for a certain project is given in the graph below with the task durations (in days) in the table beneath it. The activities d1 and d 2 are dummy activities.
What activities are on the critical path?
a,d,g
c,f,h
a,d1,e
b,e
None of the other options are correct