Question: The AOA network for a certain project is given in the graph below with the task durations ( in days ) in the table beneath
The AOA network for a certain project is given in the graph below with the task durations in days in the table beneath it The activities d and d are dummy activities.
What activities are on the critical path?
adg
cfh
ade
be
None of the other options are correct