Question: The baseline for evaluating whether requests for changes or additional work are contained within or outside the project's exclusion is provided by the Question options:

The baseline for evaluating whether requests for changes or additional work are contained within or outside the project's exclusion is provided by the

Question options:

A) WBS Dictionary

B) Project management plan

C)Project scope statement

D)Project scope management plan