The critical path for a project is: a. the sum of the shortest path of project activities
Fantastic news! We've Found the answer you've been seeking!
Question:
The critical path for a project is:
a. the sum of the shortest path of project activities
b. the sum of the longest path of project activities
c. an accumulation of random project activities
d. the least important of all project paths