Question: The critical path for the network activities shown below is with duration 1) A-D-E; 9 2) A-C-E; 14 3) A-B-C-D-E; 17 4) B-D-E; 5
The critical path for the network activities shown below is with duration 1) A-D-E; 9 2) A-C-E; 14 3) A-B-C-D-E; 17 4) B-D-E; 5 5) B-E; 4 6) B-C-E; 10 Activity Duration ImmediatePredecessors A 6 B 2 C 6 , D 1 A, B E 2 B, C, D