Question: The critical path for the network activities shown below is _ _ _ _ _ _ _ _ with duration _ _ _ _ _

The critical path for the network activities shown below is ________ with duration ________.
Activity Duration ImmediatePredecessors
A 6--
B 2--
C 6 A, B
D 1 A, B
E 2 B, C, D
Question 6 options:
1)
A-C-E; 14
2)
A-D-E; 9
3)
B-E; 4
4)
A-B-C-D-E; 17
5)
B-D-E; 5
6)
B-C-E; 10