Question: The critical path for the network activities shown below is _ _ _ _ _ _ _ _ with duration _ _ _ _ _
The critical path for the network activities shown below is with duration
Activity Duration ImmediatePredecessors
A
B
C A B
D A B
E B C D
Question options:
ACE;
ADE;
BE;
ABCDE;
BDE;
BCE;