Question: The critical path for the network activities shown below is ________ with duration ________ ActivityDuration Immediate Predecessors A2--B4--C6A,BD1A,BE2B,C,D Group of answer choices A-D-E; 5 B-E;

The critical path for the network activities shown below is ________ with duration ________

ActivityDuration

Immediate

Predecessors

A2--B4--C6A,BD1A,BE2B,C,D

Group of answer choices A-D-E; 5

B-E; 6

B-D-E; 7

A-C-E; 10

B-C-E; 12