Question: The critical path for the network activities shown below is ________ with duration ________. Activity Duration Immediate Predecessors A 2 B 4 C 6 A,
The critical path for the network activities shown below is ________ with duration ________.
| Activity | Duration | Immediate Predecessors |
| A | 2 |
|
| B | 4 |
|
| C | 6 | A, B |
| D | 1 | A, B |
| E | 2 | B, C, D |
Part 2
A. B-D-E; 7
B. A-D-E; 5
C. B-C-E; 12
D. B-E; 6
E. A-C-E; 10