Question: The critical path for the network activities shown below is with duration A. A-B-D; 10 B.C-E; 12 C.A-B-C-D-E; 22 D.A-D-E; 13 E. A-B-E; 11
The critical path for the network activities shown below is with duration A. A-B-D; 10 B.C-E; 12 C.A-B-C-D-E; 22 D.A-D-E; 13 E. A-B-E; 11