Question: The critical path for the network activities shown below is ________ with duration ________. Activity Duration Immediate Predecessors A 4 -- B 2 A C

The critical path for the network activities shown below is ________ with duration ________.

Activity

Duration

Immediate

Predecessors

A

4

--

B

2

A

C

9

--

D

4

A

E

5

B,C,D

A-D-E; 13

C-E; 14

A-B-C-D-E; 22

A-B-D; 10

A-B-E; 11