Question: The critical path for the network activities shown below is ________ with duration ________. Activity Duration Immediate Predecessors A 4 -- B 2 A C
The critical path for the network activities shown below is ________ with duration ________.
| Activity | Duration | Immediate Predecessors |
| A | 4 | -- |
| B | 2 | A |
| C | 9 | -- |
| D | 4 | A |
| E | 5 | B,C,D |
| A-D-E; 13 | ||
| C-E; 14 | ||
| A-B-C-D-E; 22 | ||
| A-B-D; 10 | ||
| A-B-E; 11 |
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
