Question: The critical path for the network activities shown below is ________ with duration ________. Activity Duration Immediate Predecessors A 2 -- B 4 -- C

The critical path for the network activities shown below is ________ with duration ________.

Activity

Duration

Immediate

Predecessors

A

2

--

B

4

--

C

6

A,B

D

1

A,B

E

2

C,D

A) A-D-E; 5

B) B-E; 6

C) B-D-E; 7

D)A-C-E; 10

E) B-C-E; 12