Question: The critical path for the network activities shown below is ________ with duration ________. Activity Duration Immediate Predecessors A 2 -- B 4 -- C
The critical path for the network activities shown below is ________ with duration ________.
| Activity | Duration | Immediate Predecessors |
| A | 2 | -- |
| B | 4 | -- |
| C | 6 | A,B |
| D | 1 | A,B |
| E | 2 | C,D |
A) A-D-E; 5
B) B-E; 6
C) B-D-E; 7
D)A-C-E; 10
E) B-C-E; 12
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
