Question: The critical path for the network activities shown below is _ _ _ _ _ with duration _ _ _ _ _ _ . Activity

The critical path for the network activities shown below is _____ with duration ______.Activity Duration Immediate PredecessorsA 4--- B2A C 7-- D4A E 5B,C,D a. A-B-D; 10b. A-B-E; 11c. C-E; 12d. A-D-E; 13e. A-B-C-D-E; 22