Question: The critical path for the network activities shown below is Activity Duration Immediate Predecessors A 4 B 2 A -- D 4 A E 5

The critical path for the network activities

The critical path for the network activities shown below is Activity Duration Immediate Predecessors A 4 B 2 A -- D 4 A E 5 B,C,D Select one: a. A-B-C-D-E b. A-B-D C. A-D-E d. C-E