Question: The critical path in a project when resource constraints are considered as well as technological constraints when defining precedence constraints is known as the critical
The critical path in a project when resource constraints are considered as well as technological constraints when defining precedence constraints is known as the critical ______.
A. path methodology (CPM)
B. chain methodology (CCM)
C. point
D. mass
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
